45 MW Power Plant: From Gas Turbine Package to Complete EPC Build

A 45 MW power plant is a practical size for many industrial sites, mines, data centre campuses and regional utilities. It is large enough to carry serious load and small enough to build without the scale of a utility megaproject. Yet many buyers discover too late that buying a 45 MW gas turbine package is not the same as owning a working 45 MW power plant.

This guide explains what a complete 45 MW power plant includes, where the equipment package ends and the plant begins, how capital cost is split, and how long each stage takes. It uses the FX-45, a new-build 45 MW gas turbine generator package from USP&E, as a worked example. Every FX-45 figure here comes from the published FX-45 product page.

USP&E has delivered 150+ power projects in 45+ countries since 2002, with 25,000 MW contracted since 2002. USP&E holds ISO 9001:2015 and ISO 45001:2018 certification and works across equipment supply, EPC (Engineering, Procurement and Construction) and O&M (Operations and Maintenance).

For a line-by-line view of the equipment scope, read the guide to what a gas turbine generator package includes. For off-grid supply, see the guide to behind the meter natural gas turbine generators, and for growth beyond one block, read how to build combined cycle power plants in phases.

What Is a 45 MW Power Plant? Specifications and Ratings

A 45 MW power plant is a complete installation that generates about 45 MW of electricity at its rated conditions. In a gas-fired plant, a gas turbine drives a generator, and the plant around it supplies fuel, removes heat, controls the process and exports power. The U.S. Energy Information Administration explains the basic process in its guide to how electricity is generated.

The FX-45 page draws a clear line. A gas turbine package is the generating equipment: turbine, gearbox, generator, controls and balance of plant, delivered as one arrangement. A gas turbine power plant is the complete installation, including civil works, the step-up transformer, grid interconnection and fuel supply.

FX-45 ratings for a 45 MW power plant block

45 MW power plant parameter

FX-45 published value

Why it matters

Rated output

45 MW at ISO conditions

Sets the plant block size

Frequency

50 Hz or 60 Hz

Must match your grid or load

Generator voltage

13.8 kV for 60 Hz; 11 kV or 15 kV for 50 Hz

Sets transformer and switchgear design

NOx emissions

25 ppmv at 15% O2, dry low NOx

Sets the permit route and any SCR need

Major inspection

48,000 equivalent operating hours

Shapes maintenance planning

Combined cycle option

2×1 block of about 135 MW, indicative

Defines the growth path

 

Source: USP&E FX-45 page. Performance figures at ISO conditions: 15 degrees Celsius, sea level, 60% relative humidity, natural gas, new and clean, at the generator terminals and a power factor of 0.8.

ISO ratings are a starting point. Heat, altitude and humidity reduce output, so a 45 MW power plant in a hot or high location will produce less. USP&E explains this in its guide to gas turbine derating for heat, altitude and site conditions.

45 MW Power Plant Cost: Package Price and Total Installed Cost

The cost of a 45 MW power plant is far more than the turbine. FX-45 pricing is issued under a non-disclosure agreement in a site-specific quotation, so no FX-45 price is quoted here. Third-party references help you test a budget.

The U.S. Energy Information Administration’s Assumptions to the Annual Energy Outlook 2026 (April 2026) puts the total overnight cost of a new industrial frame simple cycle plant at about $1,158 per kW in 2025 US dollars. On that basis, a 45 MW power plant would be in the region of $52 million installed, estimated from EIA (2026). This is a United States reference, not a USP&E price, and real sites can differ widely.

Where the money goes in a simple cycle plant

Cost component

Share of total capital cost

What it includes

Major equipment

46%

Gas turbines and emissions catalysts

Other equipment

7%

Pumps, tanks, switchgear and transformers

Construction labour

10%

Civil, structural and erection work

Materials

3%

Construction materials, freight and consumables

Engineering and construction indirects

6%

Engineering, management, start-up and commissioning

EPC fee and contingency

14%

Contractor fee and contingency

Owner’s services and contingency

11%

Development, permitting and owner’s engineering

Land, grid and gas interconnection

2%

Land, transmission line and gas pipeline connection

 

Source: shares calculated by USP&E from Table 3-1 of the Sargent & Lundy report Capital Cost and Performance Characteristics for Utility-Scale Electric Power Generating Technologies, prepared for the EIA (January 2024). Shares are rounded, indicative and exclude interest during construction.

More than half of the installed cost sits outside the major equipment. That is why the EPC contract and the owner’s scope deserve as much attention as the turbine. Grid connection is a common surprise, and USP&E covers it in its guide to grid interconnection cost.

New vs Used Equipment for a 45 MW Power Plant: Inspection, Hours and Warranty

A 45 MW power plant can be built around new or used equipment. New-build equipment brings a known configuration and warranty. Used equipment can arrive sooner but needs careful inspection.

The Electric Power Research Institute (EPRI) reported in Utility Dive in March 2026 that large new gas turbines take more than five years from order, and smaller units 18 to 36 months. USP&E states that the FX-45 is delivered in 18 to 24 months from slot reservation, with first deliveries from 2028.

New-build package compared with used units

Factor

New-build FX-45 package

Used gas turbine

Delivery

18 to 24 months from slot reservation

Months, if already built and relocated

Warranty

New-build with warranty

Usually limited or none

Configuration

Identical on every unit, one document set

Varies by unit and history

Spares

One spares catalogue across a fleet

Depends on model and age

Combined cycle

Combined cycle ready as built

Depends on design and condition

 

Source: USP&E FX-45 page for FX-45 values. Used unit factors are general practice.

If speed matters more than a new-build configuration, browse current inventory of gas turbines for sale. Every used unit needs a records audit and a borescope inspection before any deposit.

Fuel Type Comparison

Gas is one of several fuels for a plant of this size. Figures are indicative third-party references, not USP&E prices.

Fuel Type

CapEx Range

OpEx Range

Typical Lead Time

Best Application

Natural gas, industrial frame simple cycle

About $1,158/kW (EIA 2026)

About $7.18/kW per year plus $4.17/MWh (EIA 2026)

More than five years for large new units (EPRI 2026); FX-45 18 to 24 months from slot reservation

Base load and peaking blocks

Natural gas, aeroderivative simple cycle

About $2,275/kW (EIA 2026)

About $9.99/kW per year plus $5.97/MWh (EIA 2026)

18 to 36 months for smaller new units (EPRI 2026)

Fast start and peaking

Natural gas, combined cycle

About $1,032 to $1,086/kW (EIA 2026)

About $12.69 to $16.23/kW per year plus about $3.5/MWh (EIA 2026)

About 40 to 42 months from development start (Sargent & Lundy for EIA, 2024)

Efficient base load

Diesel, containerised gensets

About $650 to $880/kW installed (NREL REopt defaults)

About $10 to $20/kW per year fixed, plus fuel (NREL REopt defaults)

Often under 90 to 120 days, site dependent

Standby and short-term supply

HFO (Heavy Fuel Oil), engine power station

About $800 to $1,000/kW, medium speed engines (IDB Invest, 2010 US dollars)

Typically 9 to 14 months from deposit

Remote base load without gas

 

Sources: EIA, Assumptions to the Annual Energy Outlook 2026, Table 3 (2025 US dollars); EPRI in Utility Dive (2026); Sargent & Lundy for EIA (2024). Diesel: NREL REopt model default values (REopt generator defaults, checked 2026). HFO: IDB Invest, Liquid and Gaseous Fossil Fuel Power Plant Guidelines, citing 2010 cost data. CapEx means capital expenditure and OpEx means operating expenditure. Blank cells could not be verified from a credible public source.

Where a site also needs heat, a 45 MW power plant can be designed for combined heat and power. The U.S. Department of Energy explains the options in its combined heat and power basics. Emissions rules also shape the design. In the United States, review the U.S. Environmental Protection Agency Clean Air Act standards for engines and combustion turbines.

Building a 45 MW Power Plant: Package Supply vs EPC Contract

The FX-45 is an equipment supply scope. Equipment supply, EPC, O&M and LTSA are contracted separately, so you take only the scope you need. Below are the steps that turn a package into a working 45 MW power plant.

Step 1: Define the load, site and power date

Record peak load, growth, redundancy needs, altitude and ambient conditions. Then fix the date you need power, because every later milestone depends on it.

Step 2: Share the four sizing inputs

For the FX-45, USP&E asks for site location, gas analysis, frequency and voltage, and when you need power on. These let a supplier size the package and return a budget figure.

Step 3: Set the battery limit

The battery limit is the boundary of the package scope. On the FX-45, fuel supply to the battery limit, civil works, erection and commissioning, and the step-up transformer sit outside the package. Assign each item to a named party in writing.

Step 4: Choose the delivery model

You can buy the package and manage the rest yourself, appoint a separate contractor, or place the whole build under one EPC contract. USP&E has a dedicated centre of excellence that engineers, procures and constructs power plants, contracted separately from the package.

Step 5: Engineer the plant around the package

Plant engineering covers layout, gas conditioning, cooling, electrical systems and controls integration.

Step 6: Complete civil works and the grid connection

For a 45 MW power plant, foundations, drainage, roads, cable routes and the step-up transformer must be ready before the package lands. Grid studies and approvals should start early.

Step 7: Install, commission and test

Erection, commissioning and performance testing follow delivery. Agree the test method and acceptance criteria for the 45 MW power plant in the EPC contract.

Common 45 MW power plant mistakes to avoid

  • Treating the package price as the plant price. More than half of the installed cost sits outside major equipment.
  • Leaving the battery limit vague. Unassigned scope becomes a dispute.
  • Ordering the step-up transformer late. Electrical equipment can set the critical path.
  • Sizing on ISO ratings alone. Use a site rating.
  • Signing without service terms. Plan the LTSA and O&M with the build.
45 mw power plant

Case Studies: 45 MW Power Plant in Real Projects

First FX-45 deliveries are stated from 2028, so no FX-45 plant results exist yet. USP&E only publishes approved case studies.

A typical 45 MW power plant project starts with a site and load review, then fixes the battery limit between the package and the plant. One FX-45 package supplies the generating equipment, and a separate EPC contract covers civil works, fuel supply, the step-up transformer, erection and commissioning. USP&E supports both scopes with engineering, EPC and O&M teams that have delivered projects in 45+ countries.

The lessons below reflect common practice, not a specific project:

  • Projects that write down every battery limit item avoid disputes over civil works and fuel supply.
  • Projects that order the step-up transformer early avoid a second queue after the turbine arrives.
  • Projects that reserve space for a steam cycle can grow without moving the first block.

How to Choose a 45 MW Power Plant Contractor: 10 Criteria

Use these criteria to compare 45 MW power plant equipment and EPC offers on equal terms.

  1. Clear scope split. The offer should show what the package covers and what the EPC contract covers.
  2. Written battery limit. Every interface should have a named owner.
  3. Stated rating conditions. Ratings should state ISO conditions and the measurement point, plus a site rating.
  4. Delivery commitment. Ask for a written delivery window and what triggers it.
  5. Emissions performance. Ask for NOx levels and whether SCR is included or separate.
  6. Warranty terms. Confirm coverage and duration for equipment and works.
  7. EPC record. Ask how many plants the contractor has built. USP&E has delivered 150+ power projects in 45+ countries since 2002, supported by its power plant EPC projects team.
  8. Growth path. Confirm whether the plant can extend to combined cycle.
  9. Service support. Ask about LTSA, O&M and spares.
  10. Compliance and certification. Look for ISO 9001 and ISO 45001 certification and a written sanctions and anti-corruption policy.

FAQ: 45 MW Power Plant

How much does a 45 MW gas plant cost?

A 45 MW gas plant costs roughly $52 million installed, estimated from the EIA (2026) reference of about $1,158 per kW for a new industrial frame simple cycle plant. This is a United States reference in 2025 dollars, and FX-45 pricing is issued under a non-disclosure agreement.

What is the difference between a package and a power plant?

The package is the generating equipment, while the power plant is the complete installation. On the FX-45, the plant adds civil works, the step-up transformer, grid interconnection, fuel supply to the battery limit, erection and commissioning around the package itself.

How long does it take to build?

USP&E states that the FX-45 package is delivered in 18 to 24 months from slot reservation, with first deliveries from 2028. Civil works, gas supply, grid studies and the step-up transformer should run in parallel so the site is ready on delivery.

Who does the civil works and grid connection?

Civil works and the grid connection sit outside the FX-45 package. You can manage them yourself, appoint a separate contractor, or place them under a separate USP&E EPC contract, so that one party carries clear responsibility for the whole plant.

Can a single block grow into combined cycle?

Yes. The FX-45 is combined cycle ready as built. Two packages with heat recovery steam generators and one steam turbine form a 2×1 block of about 135 MW, indicative, so space for the steam island should be reserved from the start.

What emissions does the FX-45 produce?

The FX-45 dry low NOx combustor holds NOx to 25 ppmv at 15% O2, according to the FX-45 page. Where a permit needs single-digit NOx, SCR is available under a separate agreement and is not included in the package price.

What information does USP&E need?

USP&E needs four inputs to size a 45 MW plant: site location, gas analysis, frequency and voltage, and when you need power on. With these, USP&E can return a budget figure for the package and advise on the EPC scope around it.

Key Takeaways: 45 MW Power Plant

  • A package and a plant are different scopes. Compare both before comparing prices.
  • Major equipment is about 46% of installed cost in the EIA reference case. Budget for the rest.
  • Write down the battery limit and assign every interface.
  • Order the step-up transformer and start grid studies early.
  • Plan for growth: the FX-45 is combined cycle ready as built.

A successful 45 MW power plant depends on scope as much as equipment. Send USP&E your site location, gas analysis, frequency, voltage and power date, and its engineers will help you plan a complete 45 MW power plant, from package to grid.

Ready to Power Your Project? Talk to USP&E’s Engineers.

Whether you are in early feasibility or ready to mobilise on a power station, EPC, or O&M project, USP&E’s engineers can help. With 150+ power projects delivered in 45+ countries since 2002, our engineers remove the technical and commercial risk from your project, with speed and without excuses.

Contact USP&E Today Request a Fast Quote

USP&E: Powering Possibility. Built for the Frontier. ISO 9001:2015 | ISO 45001:2018 | 150+ power projects in 45+ countries | 25,000 MW contracted since 2002 | 24+ years

Facing a power challenge in a frontier market?
Let’s talk about how USP&E can help.