26 October 2026
As Perseus Mining heads towards first gold at its Nyanzaga Gold Project in north-western Tanzania, USP&E has put 28 MW of emergency backup power on site. USP&E worked with ECG, the Perth-based engineering consultancy that is EPCM on the project. Rather than just supplying generators, USP&E delivered a complete, engineered emergency power system. It includes 28 Cummins KTA50G3 1 MW containerised generator sets, six 72 000-litre bulk fuel tanks, three pump skids and 28 day tanks. The package was specified, integrated and delivered within the client’s budget and timeline, which kept power off the critical path for a mine where an outage could stall the ramp-up. First pour is expected in early 2027.